Difference between revisions of "EGI Infra"
m |
m |
||
(12 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
+ | = Other information = | ||
+ | |||
+ | All floor plans are available at [http://www.nikhef.nl/grid/ndpf/files/Beurs-van-Berlage/ http://www.nikhef.nl/grid/ndpf/files/Beurs-van-Berlage/] | ||
+ | |||
+ | The shipment list is at [[EGI Shipping]]. | ||
+ | |||
= Fibres = | = Fibres = | ||
{| | {| | ||
|- style="background: gray" | |- style="background: gray" | ||
− | | length || needed || order || type | + | | length || needed || order || type || ordered || confirmed || received |
|- | |- | ||
− | | 175m || 3 || 4 || rugged SM/LC-LC | + | | 175m || 3 || 4 || rugged SM/LC-LC || 20100817 || |
|- | |- | ||
− | | 80m || 4 || 5 || rugged SM/LC-LC | + | | 80m || 4 || 5 || rugged SM/LC-LC || 20100817 || |
|- | |- | ||
− | | 50m || 3 || 4 || rugged SM/LC-LC | + | | 50m || 3 || 4 || rugged SM/LC-LC || 20100817 || |
|- | |- | ||
− | | 25m || 3 || 4 || rugged SM/LC-LC | + | | 25m || 3 || 4 || rugged SM/LC-LC || 20100817 || |
|- | |- | ||
− | | 3m || 14 || 15 || regular SM/LC-LC | + | | 3m || 14 || 15 || regular SM/LC-LC || 20100817 || |
|} | |} | ||
= Fibre routes = | = Fibre routes = | ||
+ | The fibre routes extend over 4 levels, according to the [http://www.nikhef.nl/grid/ndpf/files/Beurs-van-Berlage/BvB-fibreroutes.pdf fibre route floor plan]. Please follow the descriptions below and use the correct fibre length on each of the routes. All fibres are SM/LC-LC! | ||
== Route A == | == Route A == | ||
Fibres departing from core: 3x175m + 1x80m | Fibres departing from core: 3x175m + 1x80m | ||
− | Switches: 18, 19, 20, plus one | + | Switches: 18, 19, 20, plus new "21" one in graanbeurszaal on monday |
− | To destination(s): via first floor to cellar, then via graanbeurszaal (leave 1x80m there), remaining | + | To destination(s): via first floor to cellar, then via graanbeurszaal (leave 1x80m there), remaining three continue. At mid-corridor, two go right via elevator and storage room to continue to Yakult front (leave enough fibre for truss to be raised!). At the mid-corridor, the remianing one continues to glazen zaal via massageroom and then up. |
== Route B == | == Route B == | ||
Line 55: | Line 62: | ||
To destiantion(s): to first floor, then to the truss in the beurszaal. Leave enough fibre for truss to be raised. | To destiantion(s): to first floor, then to the truss in the beurszaal. Leave enough fibre for truss to be raised. | ||
+ | |||
+ | = Switches = | ||
+ | |||
+ | Switch locaties op floor plan [http://www.nikhef.nl/grid/ndpf/files/Beurs-van-Berlage/BvB-switchlocations-200.pdf http://www.nikhef.nl/grid/ndpf/files/Beurs-van-Berlage/BvB-switchlocations-200.pdf]. | ||
+ | |||
+ | {| | ||
+ | |- style="background: gray" | ||
+ | | name || type || location || shipped || mounted || recovered || sent-back | ||
+ | |- | ||
+ | | sw06 || ?? || Zijlkamer | ||
+ | |- | ||
+ | | sw11 || 24p POE || Verweykamer patchruimte | ||
+ | |- | ||
+ | | sw12 || 24p POE || t.o. K.15 | ||
+ | |- | ||
+ | | sw13 || 24p POE || Grote zaal in truss | ||
+ | |- | ||
+ | | sw14 || 24p POE || Berlagezaal balkon 2e | ||
+ | |- | ||
+ | | sw15 || 24p POE || hal Beursfoyer onder de bank | ||
+ | |- | ||
+ | | sw16 || 24p POE || Yakult 1e truss van achteren | ||
+ | |- | ||
+ | | sw17 || 24p POE || Yakult 2e truss van achteren | ||
+ | |- | ||
+ | | sw18 || 24p POE || Yakult 2e truss van voren | ||
+ | |- | ||
+ | | sw19 || 24p POE || Yakult 1e truss van voren | ||
+ | |- | ||
+ | | sw20 || 24p POE || in de glazen zaal | ||
+ | |- | ||
+ | | sw21 || 24p POE || Graanbeurszaal buiten bij de paal ''ALLEEN OP MAANDAG'' | ||
+ | |} | ||
+ | |||
+ | = Videoconf setup = | ||
+ | |||
+ | The SD polycom (from room H135) is available, alongside a beamer and a projection screen. All components | ||
+ | come from Nikhef. | ||
+ | |||
+ | It has been reserved on the following locations | ||
+ | |||
+ | {| | ||
+ | |- style="background: gray" | ||
+ | | date || timeslot || location || requestor || session name || confirmed || placed || collected | ||
+ | |- | ||
+ | | 14 || 1400 - 1800 || da Costa || sveng || EGI CSIRT || Y || | ||
+ | |- | ||
+ | | 15 || 1100 - 1800 || da Costa || davidg || NREN GRIDS WS || Y || | ||
+ | |} | ||
+ | |||
+ | |||
+ | = Other orders = | ||
+ | |||
+ | {| | ||
+ | |- style="background: gray" | ||
+ | | product|| description || qty needed || qty ordered || ordered || confirmed || received | ||
+ | |- | ||
+ | | verlengkabel C12/C13 || div lengtes || | ||
+ | |- | ||
+ | | tie wraps || || || || 20100820 | ||
+ | |- | ||
+ | | duct tape || plakked switches op trussen || 3x50m | ||
+ | |- | ||
+ | | gaffa tape || || 8x50m | ||
+ | |- | ||
+ | | voedingen access points || 12V DC || | ||
+ | |- | ||
+ | | UTP cables || div lengtes || 55 + stands || | ||
+ | |- | ||
+ | | conversie fibre || Eurofibre afmontage -> LC | ||
+ | |} |
Latest revision as of 07:17, 27 August 2010
Other information
All floor plans are available at http://www.nikhef.nl/grid/ndpf/files/Beurs-van-Berlage/
The shipment list is at EGI Shipping.
Fibres
length | needed | order | type | ordered | confirmed | received |
175m | 3 | 4 | rugged SM/LC-LC | 20100817 | ||
80m | 4 | 5 | rugged SM/LC-LC | 20100817 | ||
50m | 3 | 4 | rugged SM/LC-LC | 20100817 | ||
25m | 3 | 4 | rugged SM/LC-LC | 20100817 | ||
3m | 14 | 15 | regular SM/LC-LC | 20100817 |
Fibre routes
The fibre routes extend over 4 levels, according to the fibre route floor plan. Please follow the descriptions below and use the correct fibre length on each of the routes. All fibres are SM/LC-LC!
Route A
Fibres departing from core: 3x175m + 1x80m
Switches: 18, 19, 20, plus new "21" one in graanbeurszaal on monday
To destination(s): via first floor to cellar, then via graanbeurszaal (leave 1x80m there), remaining three continue. At mid-corridor, two go right via elevator and storage room to continue to Yakult front (leave enough fibre for truss to be raised!). At the mid-corridor, the remianing one continues to glazen zaal via massageroom and then up.
Route B
Fibres departing from core: 2x80m + 1x50m
Switches: 15, 16, 17
To destination(s): to first floor to celler, then via beursfoyer. One goes up in beursfoyer, two continue to Yakult achter. Both go up there. Leave enough fibre for truss in Yakult to be raised!
Route C
Fibres departing from core: 3x25m
Switches: 6, 11, and EuroFiber uplink
To destiantion(s): up to first floor, then through cableduct in floor to server room (leave 1), and to patchpanel in room (2x)
Route D
Fibres departing from core: 1x80m + 1x50m
Switches: 12, 14
To destiantion(s): to second floor, then one goes over balcony to opposite side of beurszaal, and one goes via corridor to the balcony of the Berlagezaal.
Route E
Fibres departing from core: 1x50m
Switches: 13
To destiantion(s): to first floor, then to the truss in the beurszaal. Leave enough fibre for truss to be raised.
Switches
Switch locaties op floor plan http://www.nikhef.nl/grid/ndpf/files/Beurs-van-Berlage/BvB-switchlocations-200.pdf.
name | type | location | shipped | mounted | recovered | sent-back |
sw06 | ?? | Zijlkamer | ||||
sw11 | 24p POE | Verweykamer patchruimte | ||||
sw12 | 24p POE | t.o. K.15 | ||||
sw13 | 24p POE | Grote zaal in truss | ||||
sw14 | 24p POE | Berlagezaal balkon 2e | ||||
sw15 | 24p POE | hal Beursfoyer onder de bank | ||||
sw16 | 24p POE | Yakult 1e truss van achteren | ||||
sw17 | 24p POE | Yakult 2e truss van achteren | ||||
sw18 | 24p POE | Yakult 2e truss van voren | ||||
sw19 | 24p POE | Yakult 1e truss van voren | ||||
sw20 | 24p POE | in de glazen zaal | ||||
sw21 | 24p POE | Graanbeurszaal buiten bij de paal ALLEEN OP MAANDAG |
Videoconf setup
The SD polycom (from room H135) is available, alongside a beamer and a projection screen. All components come from Nikhef.
It has been reserved on the following locations
date | timeslot | location | requestor | session name | confirmed | placed | collected |
14 | 1400 - 1800 | da Costa | sveng | EGI CSIRT | Y | ||
15 | 1100 - 1800 | da Costa | davidg | NREN GRIDS WS | Y |
Other orders
product | description | qty needed | qty ordered | ordered | confirmed | received |
verlengkabel C12/C13 | div lengtes | |||||
tie wraps | 20100820 | |||||
duct tape | plakked switches op trussen | 3x50m | ||||
gaffa tape | 8x50m | |||||
voedingen access points | 12V DC | |||||
UTP cables | div lengtes | 55 + stands | ||||
conversie fibre | Eurofibre afmontage -> LC |