ITk Endcap At Nikhef

From Atlas Wiki
Revision as of 09:09, 7 June 2023 by Aalonso@nikhef.nl (talk | contribs) (→‎Cooling manifolds: add pics for manifolds and stiffener disk)
Jump to navigation Jump to search

Back to ITk Endcap Homepage

This page is meant to document all available information related to the construction of the Endcap at Nikhef.

Wheel production

Wheel conduction after assembly

Wheel Conduction

Wheel and Blade production documentation & characterisation

Wheel and Blade production documentation & characterisation

Wheel locking point measurements

Wheel locking point measurements

Wheel QA/QC

Wheel QA/QC

Inner ring measurements

Inner Ring measurements


Endcap structure

Characterization of mechanical behaviour EC structure at cold temperatures

EC structure temperature studies

Stiffener disk measurements

Stiffener disk thermal deformation tests on 21-01-2022.jpg

Stiffener Disk

PP1-patch panel

PP1 Patch Panel

Cooling manifolds

Disk 0 manifolds fabrication is not finished

All manifolds for disk 1 and disk 2 are fabricated, the As and Bs for disk 3 are fabricated as well. Disk 2, outlet manifolds A, B, C and D are cleaned by 31st May 2023.

Manifolds status 06-06-2023.jpg

Working schedule of Pranati and Ali:

- Thursday 15th: first pair of inlet manifolds, aka disk 2 inlet manifolds A and B. Then all EC1 disk 2 manifolds would be ready. And change to disk 1 inlet manifolds A and B.

- Friday 16th: move on to disk 1 outlet manifolds A and B. Then all EC1 disk 1 manifolds would be ready. And continue with disk 3 outlet manifolds A and B.

- Thursday 22nd: finish with disk 3: disk 3 inlet manifolds A and B. Then all EC1 disk 3 manifolds would be ready.

- Monday 26th: if previous days' objectives were not achieved, day to wrap things up (or do more A-B manifolds if they get ready by then). Also, Andrea García starts the pressure tests with disk 1 inlet manifolds.