=== Cooling manifolds ===
 +
Disk 0 manifolds fabrication is not finished
 +
 
 +
All manifolds for disk 1 and disk 2 are fabricated, the As and Bs for disk 3 are fabricated as well. Disk 2, outlet manifolds A, B, C and D are cleaned by 31st May 2023
 +
 
 +
Working schedule of Pranati and Ali:
 +
 
 +
- Thursday 15th: first pair of inlet manifolds (the long ones) of disk 2, aka '''disk 2 inlet manifolds A and B'''. All EC1 disk 2 manifolds would be ready.
 +
 
 +
And change to disk 1 long manifolds: '''disk 1 inlet manifolds A and B'''.
 +
 
 +
- Friday 16th: move on to short manifolds with '''disk 1 outlet manifolds A and B'''. All EC1 disk 1 manifolds would be ready.
 +
 
 +
And continue with disk 3 short manifolds: '''disk 3 outlet manifolds A and B'''.
 +
 
 +
- Thursday 22nd: finish with disk 3 long manifolds: '''disk 3 inlet manifolds A and B'''. All EC1 disk 3 manifolds would be ready.
 +
 
 +
- Monday 26th: if previous days' objectives were not achieved, day to wrap things up (or do more A-B manifolds if they get ready by then). Pressure tests start day with disk 1 manifolds.
  
 
==Cleanroom Nikhef==
 
==Cleanroom Nikhef==

Revision as of 07:56, 7 June 2023

Back to ITk Endcap Homepage

This page is meant to document all available information related to the construction of the Endcap at Nikhef.

Wheel production

Wheel conduction after assembly

Wheel Conduction

Wheel and Blade production documentation & characterisation

Wheel and Blade production documentation & characterisation

Wheel locking point measurements

Wheel locking point measurements

Wheel QA/QC

Wheel QA/QC

Inner ring measurements

Inner Ring measurements


Endcap structure

Characterization of mechanical behaviour EC structure at cold temperatures

EC structure temperature studies

Stiffener disk measurements

Stiffener Disk

PP1-patch panel

PP1 Patch Panel

Cooling manifolds

Disk 0 manifolds fabrication is not finished

All manifolds for disk 1 and disk 2 are fabricated, the As and Bs for disk 3 are fabricated as well. Disk 2, outlet manifolds A, B, C and D are cleaned by 31st May 2023

Working schedule of Pranati and Ali:

- Thursday 15th: first pair of inlet manifolds (the long ones) of disk 2, aka disk 2 inlet manifolds A and B. All EC1 disk 2 manifolds would be ready.

And change to disk 1 long manifolds: disk 1 inlet manifolds A and B.

- Friday 16th: move on to short manifolds with disk 1 outlet manifolds A and B. All EC1 disk 1 manifolds would be ready.

And continue with disk 3 short manifolds: disk 3 outlet manifolds A and B.

- Thursday 22nd: finish with disk 3 long manifolds: disk 3 inlet manifolds A and B. All EC1 disk 3 manifolds would be ready.

- Monday 26th: if previous days' objectives were not achieved, day to wrap things up (or do more A-B manifolds if they get ready by then). Pressure tests start day with disk 1 manifolds.