Difference between revisions of "ITk Endcap At Nikhef"
m (put the link to go back at the very top) |
(→Endcap structure: - add manifolds section and info) |
||
Line 30: | Line 30: | ||
===PP1-patch panel=== | ===PP1-patch panel=== | ||
− | [http://wiki.nikhef.nl/atlas/ITk_Endcap_PP1_PatchPanel PP1 Patch Panel] | + | [http://wiki.nikhef.nl/atlas/ITk_Endcap_PP1_PatchPanel PP1 Patch Panel] |
+ | |||
+ | === Cooling manifolds === | ||
+ | Disk 0 manifolds fabrication is not finished | ||
+ | |||
+ | All manifolds for disk 1 and disk 2 are fabricated, the As and Bs for disk 3 are fabricated as well. Disk 2, outlet manifolds A, B, C and D are cleaned by 31st May 2023 | ||
+ | |||
+ | Working schedule of Pranati and Ali: | ||
+ | |||
+ | - Thursday 15th: first pair of inlet manifolds (the long ones) of disk 2, aka '''disk 2 inlet manifolds A and B'''. All EC1 disk 2 manifolds would be ready. | ||
+ | |||
+ | And change to disk 1 long manifolds: '''disk 1 inlet manifolds A and B'''. | ||
+ | |||
+ | - Friday 16th: move on to short manifolds with '''disk 1 outlet manifolds A and B'''. All EC1 disk 1 manifolds would be ready. | ||
+ | |||
+ | And continue with disk 3 short manifolds: '''disk 3 outlet manifolds A and B'''. | ||
+ | |||
+ | - Thursday 22nd: finish with disk 3 long manifolds: '''disk 3 inlet manifolds A and B'''. All EC1 disk 3 manifolds would be ready. | ||
+ | |||
+ | - Monday 26th: if previous days' objectives were not achieved, day to wrap things up (or do more A-B manifolds if they get ready by then). Pressure tests start day with disk 1 manifolds. | ||
==Cleanroom Nikhef== | ==Cleanroom Nikhef== |
Revision as of 07:56, 7 June 2023
This page is meant to document all available information related to the construction of the Endcap at Nikhef.
Wheel production
Wheel conduction after assembly
Wheel and Blade production documentation & characterisation
Wheel and Blade production documentation & characterisation
Wheel locking point measurements
Wheel locking point measurements
Wheel QA/QC
Inner ring measurements
Endcap structure
Characterization of mechanical behaviour EC structure at cold temperatures
EC structure temperature studies
Stiffener disk measurements
PP1-patch panel
Cooling manifolds
Disk 0 manifolds fabrication is not finished
All manifolds for disk 1 and disk 2 are fabricated, the As and Bs for disk 3 are fabricated as well. Disk 2, outlet manifolds A, B, C and D are cleaned by 31st May 2023
Working schedule of Pranati and Ali:
- Thursday 15th: first pair of inlet manifolds (the long ones) of disk 2, aka disk 2 inlet manifolds A and B. All EC1 disk 2 manifolds would be ready.
And change to disk 1 long manifolds: disk 1 inlet manifolds A and B.
- Friday 16th: move on to short manifolds with disk 1 outlet manifolds A and B. All EC1 disk 1 manifolds would be ready.
And continue with disk 3 short manifolds: disk 3 outlet manifolds A and B.
- Thursday 22nd: finish with disk 3 long manifolds: disk 3 inlet manifolds A and B. All EC1 disk 3 manifolds would be ready.
- Monday 26th: if previous days' objectives were not achieved, day to wrap things up (or do more A-B manifolds if they get ready by then). Pressure tests start day with disk 1 manifolds.
Cleanroom Nikhef
Miscellaneous documents
- Click here for the request regarding temporary connectors (pdf).
- ITk pictures by Jesse van Dongen
- EC mockup fb2020