Difference between revisions of "Upgrade/VeloModules"

From LHCb Wiki
Jump to navigation Jump to search
Line 24: Line 24:
 
* LV (incl. PC for controls?)
 
* LV (incl. PC for controls?)
 
* DAQ
 
* DAQ
* fibres to connect to DAQ
+
* fibers to connect to DAQ
 
* database to summarize results
 
* database to summarize results
  
Line 32: Line 32:
 
* PC with PVSS to control LV and HV
 
* PC with PVSS to control LV and HV
 
* DAQ
 
* DAQ
* fibres to connect to DAQ
+
* fibers to connect to DAQ
 
* PC to run data analysis (needs to happen in real time as data volumes are very large)
 
* PC to run data analysis (needs to happen in real time as data volumes are very large)
 
* database to summarize results
 
* database to summarize results
Line 40: Line 40:
 
* if not in the cleanroom, a 'tent' to protect setup
 
* if not in the cleanroom, a 'tent' to protect setup
  
Rough schedule:
+
We will have only one DAQ system, the so-called 'mini-DAQ'. A system consists of a PCI express card in
* Q4 2016: prepare vacuum tank, cooling
+
an ASUS ESC 4000 G3 server PC. (See https://www.asus.com/us/Commercial-Servers-Workstations/ESC4000_G3/). As we have only one system, we either need to do both tests in the same place, or pull fibers.
* Q1 2017: prepare DAQ
 
  
Action list:
+
A lot of what we do depends on where we do test 2. If we do it in the clean room, then we need a blow system for the CO2. If we do it in the vacuum lab, then we need to pull a lot of optical fibers. To take this decision, we need to understand:
 +
* when is the blow system available? how often do we need to change bottles? is bottled CO2 dry and clean enough? is a blow system with cryogenic CO2 an option?
 +
* is the standard CO2 cooler reliable enough?
 +
 
 +
Things that we can prepare before the decision on the location of test 2:
 +
* finish the vacuum tank (Q4 2016)
 +
* collect LV and HV units, 19 inch rack (Q4 2016)
 +
* configure the PC for LV and HV controls (Q1 2017? does this make sense if we do not have a module yet?)
 +
* prepare DAQ system (Q1 2017)

Revision as of 17:34, 26 September 2016

Under construction


Communication

Documentation

  • project plans: 2016
  • timeline (gantt chart): 2016

Setup for module production QA (last update 22/9/2016)

There are two tests:

1. quick electrical test ("20 seconds"), mainly to check that wirebonds are ok. This test should take place in the clean-room. For this we need:

  • LV (incl. PC for controls?)
  • DAQ
  • fibers to connect to DAQ
  • database to summarize results

2. burn-in test ("24 hours"). For this we need:

  • LV
  • HV (till 1000V; must have precise current control/monitor )
  • PC with PVSS to control LV and HV
  • DAQ
  • fibers to connect to DAQ
  • PC to run data analysis (needs to happen in real time as data volumes are very large)
  • database to summarize results
  • 19 inch rack
  • CO2 cooling
  • vacuum tank
  • if not in the cleanroom, a 'tent' to protect setup

We will have only one DAQ system, the so-called 'mini-DAQ'. A system consists of a PCI express card in an ASUS ESC 4000 G3 server PC. (See https://www.asus.com/us/Commercial-Servers-Workstations/ESC4000_G3/). As we have only one system, we either need to do both tests in the same place, or pull fibers.

A lot of what we do depends on where we do test 2. If we do it in the clean room, then we need a blow system for the CO2. If we do it in the vacuum lab, then we need to pull a lot of optical fibers. To take this decision, we need to understand:

  • when is the blow system available? how often do we need to change bottles? is bottled CO2 dry and clean enough? is a blow system with cryogenic CO2 an option?
  • is the standard CO2 cooler reliable enough?

Things that we can prepare before the decision on the location of test 2:

  • finish the vacuum tank (Q4 2016)
  • collect LV and HV units, 19 inch rack (Q4 2016)
  • configure the PC for LV and HV controls (Q1 2017? does this make sense if we do not have a module yet?)
  • prepare DAQ system (Q1 2017)