Difference between revisions of "NikhefVeloTasks"
Jump to navigation
Jump to search
(→Vacuum) |
|||
Line 17: | Line 17: | ||
== Cooling == | == Cooling == | ||
* be able to put CO2-pumps under gas (e.g. for pump maintenance) | * be able to put CO2-pumps under gas (e.g. for pump maintenance) | ||
− | * theory and practice: sub-cooling on input of pump (?), control | + | * theory and practice: sub-cooling on input of pump (?), control PLC-screen, make and interprete trend plots, superheated CO2 (?), preheaters, SMS tool |
− | |||
− | |||
* special plots for TL-pump (??) | * special plots for TL-pump (??) | ||
* check long-term behaviour of system, e.g. to reduce risks of thermal runaway | * check long-term behaviour of system, e.g. to reduce risks of thermal runaway | ||
* maintain alarm levels in the alert system (PLC?) | * maintain alarm levels in the alert system (PLC?) | ||
− | * be standby 365, 24/5 to react when system switches to backup, or | + | * be standby 365, 24/5 to react when system switches to backup, or if anything else goes wrong |
− | |||
* maintain telephone numbers in PLC sms tool | * maintain telephone numbers in PLC sms tool | ||
* lend assistance to Seicar for chiller maintaince | * lend assistance to Seicar for chiller maintaince | ||
Line 30: | Line 27: | ||
* keep track of TinyTags data and dry air flow | * keep track of TinyTags data and dry air flow | ||
* order spare parts and coordinate maintenance and repair | * order spare parts and coordinate maintenance and repair | ||
− | |||
== VMC (?) == | == VMC (?) == |
Revision as of 09:50, 15 December 2016
Vacuum
- answer questions of and perform discussions with the CERN vacuum group about the new vacuum control system (Rodrigo Ferreira, Giuseppe Bregliozzi, Paulo Gomes, Henrik Vestergard)
- maintain SmsVacTool script and start it in Neon periods
- check APDP in Neon periods
- change status to ready for beam to ECS after interventions by the CERN vacuum group
Motion
- perform potmeter calibration: WinCC-panel, data-analysis, upload results to motion-PLC
- discussions with CERN PH-DT group on the new motion control system (Giovanna Lehmann, Xavier Pons and Sylvain Ravat; ([[1][meeting])
- put detectors in place after Neon periods
Cooling
- be able to put CO2-pumps under gas (e.g. for pump maintenance)
- theory and practice: sub-cooling on input of pump (?), control PLC-screen, make and interprete trend plots, superheated CO2 (?), preheaters, SMS tool
- special plots for TL-pump (??)
- check long-term behaviour of system, e.g. to reduce risks of thermal runaway
- maintain alarm levels in the alert system (PLC?)
- be standby 365, 24/5 to react when system switches to backup, or if anything else goes wrong
- maintain telephone numbers in PLC sms tool
- lend assistance to Seicar for chiller maintaince
- put system in correct state before/after Neon (setpoints, interlock?)
- keep track of TinyTags data and dry air flow
- order spare parts and coordinate maintenance and repair
VMC (?)
- check UPS systems and maintain spares (?)
- maintain email lists of UPS systems (?)
- check VMC system after yearly AUG and diesel tests (?)
- update interlock settings before/after Neon period
- take care of storage in Bld 169
- maintain manuals pages in VELO-twiki and EDMS documents
- participate in VELO run meeting on Tuesday morning
Velo upgrade
- co-coordination of WP5: keep track of anything that relates to
modules such as sensors, readout, data tapes, markers, LV- and HV-cables, components (substrates, hybrids, ...)
- participate in module-0 meeting on Tuesday
- take care of wafer and glass parts in clean room storage