Difference between revisions of "Voorbereiding verhuizing"
From PDP/Grid Wiki
Jump to navigationJump to searchLine 10: | Line 10: | ||
|- style="background:green; color:white" | |- style="background:green; color:white" | ||
| 1000 Kooimoeren bestellen || TS || week 31 | | 1000 Kooimoeren bestellen || TS || week 31 | ||
− | |- style="background: | + | |- style="background:green; color:white" |
| Bestickeren van alle te verhuizen machines || RS || week 31 | | Bestickeren van alle te verhuizen machines || RS || week 31 | ||
|- style="background:silver" | |- style="background:silver" |
Revision as of 15:07, 28 July 2009
Overzicht van de voorbereidingen van de verhuizing. Legenda: grijs=niet gedaan, groen=afgerond, rood=te laat
Voorbereidingen verhuizing NDPF | ||
---|---|---|
Taak | Wie | Wanneer |
Verticale stroomsloffen installeren | TS, RS | week 31 |
1000 Kooimoeren bestellen | TS | week 31 |
Bestickeren van alle te verhuizen machines | RS | week 31 |
Bestellen van fibers 1<->2 | DG, PK | week 31 |
Aanleggen van management netwerk | TS | week 31 |
Aanleggen fibers | TS | klaar: 3-aug |
Aanleggen guestnet verbinding salado | TS | klaar: 5-aug |
Bestellen van gereedschap setjes | TS | week 30 |
Afdek platen bestellen | TS, WH | week 31 |
opslag lade ophangen | TS | na verhuizing nikopn |
opslag lade vullen met gereedschap | TS | na ophangen |
volgorde bepalen van verhuizen / beschrijving | RS | week 31 |
spreadsheet met hosts en bekabeling | DG | week 31 |
verzamelen USB SIPs voor val, hooi-ei, 2950s | TS | week 32 |
voorbereiden virtuele WN voor tests | RS | week 32 |
drain worker nodes | RS | 7-aug |