+ | Overzicht van de voorbereidingen van de verhuizing. | ||
+ | Legenda: <font color="silver">grijs=niet gedaan</font>, <font color="green">groen=afgerond</font>, <font color="red">rood=te laat</font> | ||
+ | |||
{| style="background:silver; color:black" | {| style="background:silver; color:black" | ||
! colspan="3" style="background:blue; color:white" | Voorbereidingen verhuizing NDPF | ! colspan="3" style="background:blue; color:white" | Voorbereidingen verhuizing NDPF | ||
|- style="background:blue; color:white" | |- style="background:blue; color:white" | ||
| Taak || Wie || Wanneer | | Taak || Wie || Wanneer | ||
− | |- style="background: | + | |- style="background:red; color:white" |
| Verticale stroomsloffen installeren || TS, RS || week 31 | | Verticale stroomsloffen installeren || TS, RS || week 31 | ||
|- style="background:green; color:white" | |- style="background:green; color:white" | ||
| 1000 Kooimoeren bestellen || TS || week 31 | | 1000 Kooimoeren bestellen || TS || week 31 | ||
− | |- style="background: | + | |- style="background:green; color:white" |
| Bestickeren van alle te verhuizen machines || RS || week 31 | | Bestickeren van alle te verhuizen machines || RS || week 31 | ||
− | |- style="background: | + | |- style="background:silver" |
| Bestellen van fibers 1<->2 || DG, PK || week 31 | | Bestellen van fibers 1<->2 || DG, PK || week 31 | ||
− | |- style="background: | + | |- style="background:silver" |
| Aanleggen van management netwerk || TS || week 31 | | Aanleggen van management netwerk || TS || week 31 | ||
− | |- style="background: | + | |- style="background:silver" |
| Aanleggen fibers || TS || klaar: 3-aug | | Aanleggen fibers || TS || klaar: 3-aug | ||
− | |- style="background: | + | |- style="background:silver" |
| Aanleggen guestnet verbinding salado || TS || klaar: 5-aug | | Aanleggen guestnet verbinding salado || TS || klaar: 5-aug | ||
|- style="background:green; color:white" | |- style="background:green; color:white" | ||
Line 21: | Line 24: | ||
|- style="background:green; color: white" | |- style="background:green; color: white" | ||
| Afdek platen bestellen || TS, WH || week 31 | | Afdek platen bestellen || TS, WH || week 31 | ||
− | |- style="background: | + | |- style="background:green" |
| opslag lade ophangen || TS || na verhuizing nikopn | | opslag lade ophangen || TS || na verhuizing nikopn | ||
− | |- style="background: | + | |- style="background:silver" |
| opslag lade vullen met gereedschap || TS || na ophangen | | opslag lade vullen met gereedschap || TS || na ophangen | ||
− | |- style="background: | + | |- style="background:silver" |
| volgorde bepalen van verhuizen / beschrijving || RS || week 31 | | volgorde bepalen van verhuizen / beschrijving || RS || week 31 | ||
+ | |- style="background:silver" | ||
+ | | spreadsheet met hosts en bekabeling || DG || week 31 | ||
+ | |- style="background:green; color:white" | ||
+ | | verzamelen USB SIPs voor val, hooi-ei, 2950s || TS || week 32 | ||
+ | |- style="background:green; color: white" | ||
+ | | voorbereiden virtuele WN voor tests || RS || week 32 | ||
+ | |- style="background:silver" | ||
+ | | drain worker nodes || RS || 7-aug |
Latest revision as of 07:00, 3 August 2009
Overzicht van de voorbereidingen van de verhuizing. Legenda: grijs=niet gedaan, groen=afgerond, rood=te laat
Voorbereidingen verhuizing NDPF | ||
---|---|---|
Taak | Wie | Wanneer |
Verticale stroomsloffen installeren | TS, RS | week 31 |
1000 Kooimoeren bestellen | TS | week 31 |
Bestickeren van alle te verhuizen machines | RS | week 31 |
Bestellen van fibers 1<->2 | DG, PK | week 31 |
Aanleggen van management netwerk | TS | week 31 |
Aanleggen fibers | TS | klaar: 3-aug |
Aanleggen guestnet verbinding salado | TS | klaar: 5-aug |
Bestellen van gereedschap setjes | TS | week 30 |
Afdek platen bestellen | TS, WH | week 31 |
opslag lade ophangen | TS | na verhuizing nikopn |
opslag lade vullen met gereedschap | TS | na ophangen |
volgorde bepalen van verhuizen / beschrijving | RS | week 31 |
spreadsheet met hosts en bekabeling | DG | week 31 |
verzamelen USB SIPs voor val, hooi-ei, 2950s | TS | week 32 |
voorbereiden virtuele WN voor tests | RS | week 32 |
drain worker nodes | RS | 7-aug |