Difference between revisions of "VUVProjectsPlanning"
m (→Update March 2023:  Update planning)  | 
				 (→Update March 2023:  Update planning)  | 
				||
| Line 91: | Line 91: | ||
|-  | |-  | ||
| Set up V1730 digitisers/read-out computer || Marjolein ||    | | Set up V1730 digitisers/read-out computer || Marjolein ||    | ||
| − | |  | + | |testing  | 
| March  | | March  | ||
|-  | |-  | ||
| − | |Get SiPM holder made (3x3 mm SiPM, teflon or other suitable plastic)  | + | |<s>Get SiPM holder made (3x3 mm SiPM, teflon or other suitable plastic)</s>  | 
|Marjolein  | |Marjolein  | ||
|  | |  | ||
| − | |  | + | |done  | 
|March  | |March  | ||
|-  | |-  | ||
| − | |Re-configure the sample chamber for reflectance measurements  | + | |<s>Re-configure the sample chamber for reflectance measurements</s>  | 
|Marjolein/Vikas  | |Marjolein/Vikas  | ||
|  | |  | ||
| Line 112: | Line 112: | ||
|April  | |April  | ||
|-  | |-  | ||
| − | | CAD model of setup; study geometry of light paths and sample/detectors || Marjolein ||    | + | | <s>CAD model of setup; study geometry of light paths and sample/detectors</s> || Marjolein ||    | 
| − | |  | + | |done  | 
|    | |    | ||
|-  | |-  | ||
| Line 122: | Line 122: | ||
|  | |  | ||
|-  | |-  | ||
| − | | Move setup back to old lab || all ||    | + | | <s>Move setup back to old lab</s> || all ||    | 
| − | | || March  | + | | done|| March  | 
|-  | |-  | ||
|Make sure all chemicals for sample cleaning procedure are available; clean samples  | |Make sure all chemicals for sample cleaning procedure are available; clean samples  | ||
| Line 137: | Line 137: | ||
| ||  | | ||  | ||
|-  | |-  | ||
| − | | Summarise optics inputs to MC in DUNE, and if available, other LAr detectors || Marjolein ||    | + | | <s>Summarise optics inputs to MC in DUNE, and if available, other LAr detectors</s> || Marjolein ||    | 
| − | |   | + | | done  | 
|    | |    | ||
|-  | |-  | ||
| Line 274: | Line 274: | ||
|Oct 7 (Oct 20 for the new board)  | |Oct 7 (Oct 20 for the new board)  | ||
|-  | |-  | ||
| − | |Design SiPM array holder for fluorescence  | + | |<s>Design SiPM array holder for fluorescence</s>  | 
|Marjolein/Emily  | |Marjolein/Emily  | ||
|Preliminary analysis of sensitivity needs finished  | |Preliminary analysis of sensitivity needs finished  | ||
| − | |  | + | |Done  | 
|Nov  | |Nov  | ||
|-  | |-  | ||
| − | |Design SiPM array holder for reflectance/transmission  | + | |<s>Design SiPM array holder for reflectance/transmission</s>  | 
|Marjolein  | |Marjolein  | ||
|Analysis of physics goals finished  | |Analysis of physics goals finished  | ||
| − | |  | + | |Done  | 
|Nov  | |Nov  | ||
|-  | |-  | ||
| Line 368: | Line 368: | ||
Tina:    | Tina:    | ||
| − | *   | + | * April 5 - April 11  | 
| − | *   | + | * April 4 - 5 (Veldhoven)  | 
| − | *   | + | * April 17 - 18?  | 
Marjolein:  | Marjolein:  | ||
| − | *   | + | * April 3 and 17 (taking charge of your phD)  | 
| − | *   | + | * April 4 - 5 (Veldhoven)  | 
| − | + | * April 12 - 14 (topical lectures)  | |
| − | |||
| − | |||
| − | |||
| − | *   | ||
| − | |||
Vikas:  | Vikas:  | ||
Revision as of 15:43, 6 April 2023
Update March 2023
| Projects | DRI | Main dependencies | Status | Finish by | 
|---|---|---|---|---|
| Measure fluorescence efficiency of PTFE | ||||
| Measure reflectance of cryostat components | Marjolein | |||
| Measure optical properties of Arapuca components | Vikas | |||
| Measure the spectrum of the D2 lamp | Jasmijn | Done | Dec 1 | |
| Gain characterization of SiPMs | ||||
| Measure excitation beam intensity as function of SiPM position and slit width | Tomas | |||
| Measure time stability of D2 lamp intensity | ||||
| DN vs temperature characterization of SiPMs | Lucia | Done | Feb 4 or 7 | |
| Continue DN vs temp measurements | BSc internship students | End of June | ||
| Determine effect of exposure to radiation on fluorescence of plastics | 
| Task | DRI | Dependencies | Status | Date | 
|---|---|---|---|---|
| Have sample storage box made (3D print) | Vikas | prototype done | Feb | |
| Sort out data storage with PDP group | Tina/Marjolein | done | Feb | |
| DN vs temperature characterization of VUV SiPMs | moved to June | |||
| Set up V1730 digitisers/read-out computer | Marjolein | testing | March | |
| Marjolein | done | March | ||
| Marjolein/Vikas | done | March | ||
| Set up upgraded slow control system | Vikas | April | ||
| Marjolein | done | |||
| Design dsub plug for use on vacuum side to make cable connections easier | ||||
| all | done | March | ||
| Make sure all chemicals for sample cleaning procedure are available; clean samples | Vikas | April | ||
| Put together a summary of previous VUV reflectance measurements (new site here), as well as any results for Al and/or similar metals, if time, also for PTFE | Vikas | |||
| Marjolein | done | |||
Outdated below here
| Task (move and January DC project) | DRI | dependencies | Status | Deadline | 
|---|---|---|---|---|
| Emily and Marjolein | Boxes arrived | Done | Dec 13 | |
| Emily and Marjolein | Done | Dec 13 | ||
| Marjolein | Done | Dec 12 | ||
| Tina | Dec 16 | |||
| Power supply for Peltier element | Dec 16 | |||
| Vikas (Lucia, Tina) | Done | Jan 12 | ||
| Vikas (Lucia) | Temperature range might need to be increased for future dark box measurements. Unlikely to go below 0° for full setup atm. | Done | Jan 13 | |
| Marjolein (Lucia) | Done | Jan 20 | ||
| Lucia | Done | Jan 27 | ||
| Task (hardware) | DRI | Main dependencies | Status | Finish by | 
|---|---|---|---|---|
| Marjolein | Vikas | Done | Sept 23 | |
| Emily | Done | Sept 23 | ||
| Emily | Done | Sept 27 | ||
| Emily | Done | Oct 1 | ||
-  -  -  -   | 
Marjolein (Jasmijn) | Pressure read-out working | Done | Oct 1 | 
| SiPM signal output
 -  -  -  -  -   | 
Emily | Vacuum/light leak eliminated | Done | Oct 7 (Oct 20 for the new board) | 
| Marjolein/Emily | Preliminary analysis of sensitivity needs finished | Done | Nov | |
| Marjolein | Analysis of physics goals finished | Done | Nov | |
| Marjolein (Jasmijn) | Nov | |||
| Emily | Done | Nov | ||
| Emily Marjolein | Minimum working setup | Dec | ||
| Install cooling system (LN2 plate, thermal shorts, LN2 fill system, super insulation) | Emily | Delivery of components/LN2 approval for lab | Dec/Jan | |
| Set up slow-control read-out and data storage, monochromator motor control | Vikas -> ? | Jan | 
| Task (review and calculations) | DRI | Status | Finish by | 
|---|---|---|---|
| Emily (Jasmijn) | Done | Oct 28 | |
| Marjolein | Done | Oct 30 | |
Link to measurement procedure document: File:Measurement procedure.pdf
Update August 2022
PhDs:
Vikas: At CERN until end of the year. Will work a little bit with CT technician to get code and slow control in good shape.
Emily: Focus on getting the SiPM signals to the digitisers. Work with Hans from ET department.
Marjolein: Focus on getting the data from the digitisers into a good format. Work with Maricke/Joran to copy XAMS read-out software.
Undergraduates:
Ilze (start Sept 12, HBO internship): Get vacuum chamber working correctly, design improved SiPM holder. Measure beam intensity as function of distance using SiPM
Jasmijn (start Sept, AUC capstone project): Measure lamp spectrum. Based on expected PTFE fluorescence efficiency, calculate amount of light expected on SiPM, and whether that is measurable over the DC rate
Not free: Monday 11-14, Tuesday 11-13, Wednesday 9-12, Thursday 16-18, Friday 16-18
Lucia (January 2023): Measure the SiPM DC rate as a function of temperature. About 6 hours per day.
Projects for distibution
- SiPM array and holder --> reflectivity design (modelling/ mechanical viability/ feedthrough positioning)
 - SiPM array and holder --> fluorescence design (modelling/ mechanical viability/ movement inside chamber/ solid angle coverage)
 - Cooling system for sample holder/SiPMs (CAD/COMSOL/ LN2 bath)
 - Put together a plan for data taking
 
Vacations
Tina:
- April 5 - April 11
 - April 4 - 5 (Veldhoven)
 - April 17 - 18?
 
Marjolein:
- April 3 and 17 (taking charge of your phD)
 - April 4 - 5 (Veldhoven)
 - April 12 - 14 (topical lectures)
 
Vikas: