Difference between revisions of "VUVProjectsPlanning"
| Line 123: | Line 123: | ||
|- | |- | ||
|Design SiPM array holder for fluorescence | |Design SiPM array holder for fluorescence | ||
| − | | | + | |Marjolein |
|Preliminary analysis of sensitivity needs finished | |Preliminary analysis of sensitivity needs finished | ||
| | | | ||
| Line 134: | Line 134: | ||
|Nov | |Nov | ||
|- | |- | ||
| − | |<s>Get SiPM signal to disk | + | |<s>Get SiPM signal to disk such that single-pulse rates can be measured (programmable CAEN digitizer for now, V1720 with XAMS-like read-out later)</s> |
|Marjolein (Jasmijn) | |Marjolein (Jasmijn) | ||
| | | | ||
| Line 140: | Line 140: | ||
|Nov | |Nov | ||
|- | |- | ||
| − | |Calibrations start | + | |<s>Calibrations start</s> |
|Emily Marjolein | |Emily Marjolein | ||
|Minimum working setup | |Minimum working setup | ||
| | | | ||
| − | | | + | |Dec |
|- | |- | ||
| − | |Get sample holder (fluorescence design) built | + | |<s>Get sample holder (fluorescence design) built</s> |
|Emily | |Emily | ||
| | | | ||
| Line 152: | Line 152: | ||
|Nov | |Nov | ||
|- | |- | ||
| + | |Install cooling system (LN2 plate, thermal shorts, LN2 fill system, super insulation) | ||
| + | |Emily | ||
| + | |Delivery of components/LN2 approval for lab | ||
| + | | | ||
| + | |Dec/Jan | ||
| + | | | ||
|Set up slow-control read-out and data storage, monochromator motor control | |Set up slow-control read-out and data storage, monochromator motor control | ||
|Vikas -> ? | |Vikas -> ? | ||
| | | | ||
| | | | ||
| − | | | + | |Jan |
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
|} | |} | ||
{| class="wikitable" | {| class="wikitable" | ||
Revision as of 13:11, 6 December 2022
Update September 2022
| Task (measurements) | DRI | Main dependencies | Status | Finish by |
|---|---|---|---|---|
| Measure fluorescence efficiency of PTFE | Emily | |||
| Measure reflectance of cryostat components | Marjolein | |||
| Measure optical properties of Arapuca components | Vikas | |||
| Measure the spectrum of the D2 lamp | Jasmijn | Dec 1 (?) | ||
| Gain characterization of SiPMs | Jasmijn | |||
| Measure excitation beam intensity as function of SiPM position and slit width | ||||
| Measure time stability of D2 lamp intensity | ||||
| DN vs temperature characterization of SiPMs | ||||
| Determine effect of exposure to radiation on fluorescence of plastics |
| Task (hardware) | DRI | Main dependencies | Status | Finish by | ||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Marjolein | Vikas | Done | Sept 23 | |||||||
| Emily | Done | Sept 23 | ||||||||
| Emily | Done | Sept 27 | ||||||||
| Emily | Done | Oct 1 | ||||||||
- - - - |
Marjolein (Jasmijn) | Pressure read-out working | Done | Oct 1 | ||||||
| SiPM signal output
- - - - - |
Emily | Vacuum/light leak eliminated | Done | Oct 7 (Oct 20 for the new board) | ||||||
| Design SiPM array holder for fluorescence | Marjolein | Preliminary analysis of sensitivity needs finished | Nov | |||||||
| Design SiPM array holder for reflectance/transmission | Marjolein | Analysis of physics goals finished | Nov | |||||||
| Marjolein (Jasmijn) | Nov | |||||||||
| Emily Marjolein | Minimum working setup | Dec | ||||||||
| Emily | Done | Nov | ||||||||
| Install cooling system (LN2 plate, thermal shorts, LN2 fill system, super insulation) | Emily | Delivery of components/LN2 approval for lab | Dec/Jan | Set up slow-control read-out and data storage, monochromator motor control | Vikas -> ? | Jan |
| Task (review and calculations) | DRI | Status | Finish by |
|---|---|---|---|
| Estimate sensitivity needs of the PTFE fluorescence measurement (preliminary, rough calculation) | Emily (Jasmijn) | Oct 28 | |
| Review past reflectivity setup design/sample holder (that had XENON in mind) in light of DUNE needs | Marjolein | Oct 30 | |
Update August 2022
PhDs:
Vikas: At CERN until end of the year. Will work a little bit with CT technician to get code and slow control in good shape.
Emily: Focus on getting the SiPM signals to the digitisers. Work with Hans from ET department.
Marjolein: Focus on getting the data from the digitisers into a good format. Work with Maricke/Joran to copy XAMS read-out software.
Undergraduates:
Ilze (start Sept 12, HBO internship): Get vacuum chamber working correctly, design improved SiPM holder. Measure beam intensity as function of distance using SiPM
Jasmijn (start Sept, AUC capstone project): Measure lamp spectrum. Based on expected PTFE fluorescence efficiency, calculate amount of light expected on SiPM, and whether that is measurable over the DC rate
Not free: Monday 11-14, Tuesday 11-13, Wednesday 9-12, Thursday 16-18, Friday 16-18
Lucia (January 2023): Measure the SiPM DC rate as a function of temperature
Projects for distibution
- SiPM array and holder --> reflectivity design (modelling/ mechanical viability/ feedthrough positioning)
- SiPM array and holder --> fluorescence design (modelling/ mechanical viability/ movement inside chamber/ solid angle coverage)
- Cooling system for sample holder/SiPMs (CAD/COMSOL/ LN2 bath)
- Put together a plan for data taking