| Line 69: | Line 69: | ||
!Status  | !Status  | ||
!Finish by  | !Finish by  | ||
| − | |  | + | |-  | 
| + | |Leak check vacuum system and fix leaks  | ||
| + | |Marjolein (Jasmijn)  | ||
| + | |Pressure read-out working  | ||
| + | |  | ||
| + | |Oct 1  | ||
| + | |-  | ||
| + | |Get sample holder (fluorescence design) built  | ||
|Emily  | |Emily  | ||
|  | |  | ||
|  | |  | ||
| − | |  | + | |Nov  | 
|-  | |-  | ||
| − | |  | + | |Cooling system for sample/SiPM planning and component ordering (design, simulations, quotes for components)  | 
|Emily  | |Emily  | ||
|  | |  | ||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
|  | |  | ||
| − | |  | + | |Sept 27  | 
|-  | |-  | ||
|Design SiPM array holder for fluorescence  | |Design SiPM array holder for fluorescence  | ||
|Emily  | |Emily  | ||
|Preliminary analysis of sensitivity needs finished  | |Preliminary analysis of sensitivity needs finished  | ||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
|  | |  | ||
|Oct 17  | |Oct 17  | ||
| Line 105: | Line 100: | ||
|Oct 30  | |Oct 30  | ||
|-  | |-  | ||
| + | |Get SiPM signal out of vacuum (1 channel for now, 9 channels eventually)  | ||
| + | |Emily  | ||
| + | |  | ||
| + | |Mostly done  | ||
| + | |Sept 27  | ||
|-  | |-  | ||
| − | + | |Get SiPM signal to disk such that single-pulse rates can be measured (programmable CAEN digitizer for now, V1720 with XAMS-like read-out later)  | |
| − | |Get   | + | |Marjolein (Jasmijn)  | 
| − | |  | ||
|  | |  | ||
|  | |  | ||
| − | |  | + | |Oct 17  | 
|-  | |-  | ||
|Set up slow-control read-out and data storage, monochromator motor control  | |Set up slow-control read-out and data storage, monochromator motor control  | ||
Revision as of 12:09, 20 September 2022
Update September 2022
| Task (measurements) | DRI | Main dependencies | Status | Finish by | 
|---|---|---|---|---|
| Measure fluorescence efficiency of PTFE | Emily | |||
| Measure reflectance of cryostat components | Marjolein | |||
| Measure optical properties of Arapuca components | Vikas | |||
| Measure the spectrum of the D2 lamp | Jasmijn | Dec 1 | ||
| Gain characterization of SiPMs | Jasmijn | |||
| Measure excitation beam intensity as function of SiPM position and slit width | ||||
| Measure time stability of D2 lamp intensity | ||||
| DN vs temperature characterization of SiPMs | ||||
| Determine effect of exposure to radiation on fluorescence of plastics | 
| Task (hardware) | DRI | Main dependencies | Status | Finish by | 
|---|---|---|---|---|
| Leak check vacuum system and fix leaks | Marjolein (Jasmijn) | Pressure read-out working | Oct 1 | |
| Get sample holder (fluorescence design) built | Emily | Nov | ||
| Cooling system for sample/SiPM planning and component ordering (design, simulations, quotes for components) | Emily | Sept 27 | ||
| Design SiPM array holder for fluorescence | Emily | Preliminary analysis of sensitivity needs finished | Oct 17 | |
| Design SiPM array holder for reflectance/transmission | Marjolein | Analysis of physics goals finished | Oct 30 | |
| Get SiPM signal out of vacuum (1 channel for now, 9 channels eventually) | Emily | Mostly done | Sept 27 | |
| Get SiPM signal to disk such that single-pulse rates can be measured (programmable CAEN digitizer for now, V1720 with XAMS-like read-out later) | Marjolein (Jasmijn) | Oct 17 | ||
| Set up slow-control read-out and data storage, monochromator motor control | Vikas -> ? | Dec | ||
| Install cooling system (LN2 plate, thermal shorts, LN2 fill system, super insulation) | Emily | Dec | ||
| Task (review and calculations) | DRI | Status | Finish by | 
|---|---|---|---|
| Estimate sensitivity needs of the PTFE fluorescence measurement (preliminary, rough calculation) | Emily (Jasmijn) | Oct 17 | |
| Review past reflectivity setup design/sample holder (that had XENON in mind) in light of DUNE needs | Marjolein | Oct 30 | |
Update August 2022
PhDs:
Vikas: At CERN until end of the year. Will work a little bit with CT technician to get code and slow control in good shape.
Emily: Focus on getting the SiPM signals to the digitisers. Work with Hans from ET department.
Marjolein: Focus on getting the data from the digitisers into a good format. Work with Maricke/Joran to copy XAMS read-out software.
Undergraduates:
Ilze (start Sept 12, HBO internship): Get vacuum chamber working correctly, design improved SiPM holder. Measure beam intensity as function of distance using SiPM
Jasmijn (start Sept, AUC capstone project): Estimate fluorescence efficiency of PTFE based on Xenon lone-S2 rates. Measure lamp spectrum.
Not free: Monday 11-14, Tuesday 11-13, Wednesday 9-12, Thursday 16-18, Friday 16-18
Lucia (January 2023): Measure the SiPM DC rate as a function of temperature
Projects for distibution
- SiPM array and holder --> reflectivity design (modelling/ mechanical viability/ feedthrough positioning)
 - SiPM array and holder --> fluorescence design (modelling/ mechanical viability/ movement inside chamber/ solid angle coverage)
 - Cooling system for sample holder/SiPMs (CAD/COMSOL/ LN2 bath)
 - Put together a plan for data taking