| Line 33: | Line 33: | ||
|-  | |-  | ||
|Gain characterization of SiPMs  | |Gain characterization of SiPMs  | ||
| − | |  | + | |  | 
|  | |  | ||
|  | |  | ||
| Line 51: | Line 51: | ||
|-  | |-  | ||
|DN vs temperature characterization of SiPMs  | |DN vs temperature characterization of SiPMs  | ||
| + | |<u>Lucia</u>  | ||
| + | |  | ||
| + | |  | ||
| + | |Feb 4  | ||
| + | |-  | ||
| + | |Determine effect of exposure to radiation on fluorescence of plastics  | ||
| + | |  | ||
| + | |  | ||
| + | |  | ||
| + | |  | ||
| + | |}  | ||
| + | {| class="wikitable"  | ||
| + | |+  | ||
| + | !Task (move and January DC project)  | ||
| + | !DRI  | ||
| + | !dependencies   | ||
| + | !Status   | ||
| + | !Deadline  | ||
| + | |-  | ||
| + | |Pack all tools and parts that belong to the VUV setup in boxes  | ||
| + | |Emily and Marjolein  | ||
| + | |Boxes arrived  | ||
| + | |  | ||
| + | |Dec 13  | ||
| + | |-  | ||
| + | |Put the DAQ for the SiPM and the temperature readout equipment together so the complete system necessary for DC rate measurement can be moved independently. Room is TBD  | ||
| + | |Emily and Marjolein  | ||
|  | |  | ||
|  | |  | ||
| + | |Dec 13  | ||
| + | |-  | ||
| + | |Check if the VUV setup table fits through the corridor. If not, we have to disassemble so let's hope it fits.  | ||
| + | |Marjolein  | ||
|  | |  | ||
|  | |  | ||
| + | |Dec 12  | ||
|-  | |-  | ||
| − | |  | + | |Identify dark box to be used for DC measurement.  | 
| + | |Tina  | ||
| + | |  | ||
| + | |  | ||
| + | |Dec 16  | ||
| + | |-  | ||
| + | |Test Peltier element and plan how to integrate it in the dark box and with the SiPM and PT100  | ||
| + | |  | ||
| + | |Power supply for Peltier element  | ||
| + | |  | ||
| + | |Dec 16  | ||
| + | |-  | ||
| + | |Set up PT100 read-out and SiPM read-out through dark box  | ||
| + | |Vikas (Lucia, Tina)  | ||
| + | |  | ||
| + | |  | ||
| + | |Jan 12  | ||
| + | |-  | ||
| + | |Develop procedure to keep SiPM at specific temperature for ~15 minutes at a time (what voltage/current is needed?) and determine if a large enough temperature range is accessible with this element (if not, ask Tina to order the next size up)  | ||
| + | |Vikas (Lucia)  | ||
| + | |  | ||
| + | |  | ||
| + | |Jan 13  | ||
| + | |-  | ||
| + | |Script to plot DC rates as function of temperature  | ||
| + | |Marjolein (Lucia)  | ||
| + | |  | ||
| + | |  | ||
| + | |Jan 20  | ||
| + | |-  | ||
| + | |Script to fit the "DC rate versus temperature" curve   | ||
| + | |Lucia  | ||
| + | |  | ||
| + | |  | ||
| + | |Jan 27  | ||
| + | |-  | ||
| + | |  | ||
|  | |  | ||
|  | |  | ||
| Line 199: | Line 267: | ||
<s>Ilze (start Sept 12, HBO internship): Get vacuum chamber working correctly, design improved SiPM holder. Measure beam intensity as function of distance using SiPM</s>  | <s>Ilze (start Sept 12, HBO internship): Get vacuum chamber working correctly, design improved SiPM holder. Measure beam intensity as function of distance using SiPM</s>  | ||
| − | Jasmijn (start Sept, AUC capstone project):  Measure lamp spectrum. Based on expected PTFE fluorescence efficiency, calculate amount of light expected on SiPM, and whether that is measurable over the DC rate  | + | '''Jasmijn''' (start Sept, AUC capstone project):  Measure lamp spectrum. Based on expected PTFE fluorescence efficiency, calculate amount of light expected on SiPM, and whether that is measurable over the DC rate  | 
Not free: Monday 11-14, Tuesday 11-13, Wednesday 9-12, Thursday 16-18, Friday 16-18  | Not free: Monday 11-14, Tuesday 11-13, Wednesday 9-12, Thursday 16-18, Friday 16-18  | ||
| − | Lucia (January 2023): Measure the SiPM DC rate as a function of temperature  | + | |
| + | '''Lucia''' (January 2023): Measure the SiPM DC rate as a function of temperature. About 6 hours per day.  | ||
======Projects for distibution======  | ======Projects for distibution======  | ||
Revision as of 13:51, 7 December 2022
Update September 2022
| Task (measurements) | DRI | Main dependencies | Status | Finish by | 
|---|---|---|---|---|
| Measure fluorescence efficiency of PTFE | Emily | |||
| Measure reflectance of cryostat components | Marjolein | |||
| Measure optical properties of Arapuca components | Vikas | |||
| Measure the spectrum of the D2 lamp | Jasmijn | Dec 1 (?) | ||
| Gain characterization of SiPMs | ||||
| Measure excitation beam intensity as function of SiPM position and slit width | ||||
| Measure time stability of D2 lamp intensity | ||||
| DN vs temperature characterization of SiPMs | Lucia | Feb 4 | ||
| Determine effect of exposure to radiation on fluorescence of plastics | 
| Task (move and January DC project) | DRI | dependencies | Status | Deadline | 
|---|---|---|---|---|
| Pack all tools and parts that belong to the VUV setup in boxes | Emily and Marjolein | Boxes arrived | Dec 13 | |
| Put the DAQ for the SiPM and the temperature readout equipment together so the complete system necessary for DC rate measurement can be moved independently. Room is TBD | Emily and Marjolein | Dec 13 | ||
| Check if the VUV setup table fits through the corridor. If not, we have to disassemble so let's hope it fits. | Marjolein | Dec 12 | ||
| Identify dark box to be used for DC measurement. | Tina | Dec 16 | ||
| Test Peltier element and plan how to integrate it in the dark box and with the SiPM and PT100 | Power supply for Peltier element | Dec 16 | ||
| Set up PT100 read-out and SiPM read-out through dark box | Vikas (Lucia, Tina) | Jan 12 | ||
| Develop procedure to keep SiPM at specific temperature for ~15 minutes at a time (what voltage/current is needed?) and determine if a large enough temperature range is accessible with this element (if not, ask Tina to order the next size up) | Vikas (Lucia) | Jan 13 | ||
| Script to plot DC rates as function of temperature | Marjolein (Lucia) | Jan 20 | ||
| Script to fit the "DC rate versus temperature" curve | Lucia | Jan 27 | ||
| Task (hardware) | DRI | Main dependencies | Status | Finish by | 
|---|---|---|---|---|
| Marjolein | Vikas | Done | Sept 23 | |
| Emily | Done | Sept 23 | ||
| Emily | Done | Sept 27 | ||
| Emily | Done | Oct 1 | ||
-  -  -  -   | 
Marjolein (Jasmijn) | Pressure read-out working | Done | Oct 1 | 
| SiPM signal output
 -  -  -  -  -   | 
Emily | Vacuum/light leak eliminated | Done | Oct 7 (Oct 20 for the new board) | 
| Design SiPM array holder for fluorescence | Marjolein/Emily | Preliminary analysis of sensitivity needs finished | Started | Nov | 
| Design SiPM array holder for reflectance/transmission | Marjolein | Analysis of physics goals finished | Nov | |
| Marjolein (Jasmijn) | Nov | |||
| Emily | Done | Nov | ||
| Emily Marjolein | Minimum working setup | Dec | ||
| Install cooling system (LN2 plate, thermal shorts, LN2 fill system, super insulation) | Emily | Delivery of components/LN2 approval for lab | Dec/Jan | |
| Set up slow-control read-out and data storage, monochromator motor control | Vikas -> ? | Jan | 
| Task (review and calculations) | DRI | Status | Finish by | 
|---|---|---|---|
| Emily (Jasmijn) | Done | Oct 28 | |
| Marjolein | Done | Oct 30 | |
Update August 2022
PhDs:
Vikas: At CERN until end of the year. Will work a little bit with CT technician to get code and slow control in good shape.
Emily: Focus on getting the SiPM signals to the digitisers. Work with Hans from ET department.
Marjolein: Focus on getting the data from the digitisers into a good format. Work with Maricke/Joran to copy XAMS read-out software.
Undergraduates:
Ilze (start Sept 12, HBO internship): Get vacuum chamber working correctly, design improved SiPM holder. Measure beam intensity as function of distance using SiPM
Jasmijn (start Sept, AUC capstone project): Measure lamp spectrum. Based on expected PTFE fluorescence efficiency, calculate amount of light expected on SiPM, and whether that is measurable over the DC rate
Not free: Monday 11-14, Tuesday 11-13, Wednesday 9-12, Thursday 16-18, Friday 16-18
Lucia (January 2023): Measure the SiPM DC rate as a function of temperature. About 6 hours per day.
Projects for distibution
- SiPM array and holder --> reflectivity design (modelling/ mechanical viability/ feedthrough positioning)
 - SiPM array and holder --> fluorescence design (modelling/ mechanical viability/ movement inside chamber/ solid angle coverage)
 - Cooling system for sample holder/SiPMs (CAD/COMSOL/ LN2 bath)
 - Put together a plan for data taking