Upgrade/RFFoil

From LHCb Wiki
Jump to navigation Jump to search

Communication

Planning

Link to project plan: [project plan]

Rough timeline:

  • R&D/prototyping 2014-2016
  • Production 2017-2018
  • Installation 2019

See also our [Gantt chart].

OPP reports: [2014/02/04], [2014/04/15], [2014/07/04], [2014/09/16], [2014/10/21], [2014/12/02]

People

  • Willem Kuilman
  • Johan Kos
  • Berend Munneke
  • Krista de Roo
  • Erno Roeland
  • Martin Doets
  • Rob Walet
  • Tjeerd Ketel
  • Wouter Hulsbergen

3D model, drawings

The CATIA model and stp files for the RF box can be found on Martin's webpage:

http://www.nikhef.nl/~martind/Velo%20boxes/

Requirements

File:Requirements.pdf is the information given to external partners.

Information on materials

Machining

  • File:Mul Milling vs Turning.pdf is an old presentation by Frans Mul. The interesting conclusion is that 'turning' leads to a leaking foil, while 'milling' does not.

Fixing leaks

NEG coating

Vacuum measurements

Presentations

This is a very small subset!

  • 2015/02/05: [[1] W. Hulsbergen, CERN RF box workshop]

Activities/milestones reached