Difference between revisions of "Upgrade/RFFoil"
Jump to navigation
Jump to search
Line 79: | Line 79: | ||
* 2012/03/08: [[File:PhotosLeakMilledFoil_TjeerdKetel_20120308.pdf]] T. Ketel, SEM-EDS analysis of leak in VU-MC Box 1 | * 2012/03/08: [[File:PhotosLeakMilledFoil_TjeerdKetel_20120308.pdf]] T. Ketel, SEM-EDS analysis of leak in VU-MC Box 1 | ||
− | == Activities == | + | == Activities/milestones reached == |
− | + | * 2015/10/29: Vacuum tests show the box is vacuum tight: | |
− | * | + | * 2015/10/01: Milling now completely finished! |
+ | * 2015/09/17: Milling of outside is finished, apart from side that has wakefield connectors | ||
+ | * photos taken by Tjeerd: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/2015/documents/photohb2.pdf | ||
+ | * 2015/09/03: Mold positioned inside box and space filled with wax | ||
+ | * 2015/08/20: Inside milling finished | ||
+ | * metrology report: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/2015/documents/HalfboxA.pdf | ||
+ | * photos taken by Tjeerd: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/2015/documents/photohb.pdf | ||
+ | * 2015/: Outside milled to +1 cm. This is how it will stay until inside is finished | ||
+ | * 2015/03/19: Mold finished | ||
+ | * 2014/12: Started milling of the mold | ||
* 2014/10/20: Three drums with 0.1 micron holes sent to VDL (see ELOG) | * 2014/10/20: Three drums with 0.1 micron holes sent to VDL (see ELOG) | ||
* 2014/10/20: Received 1kg of Field's metal and 1kg of cerrolow 136 from Lowden Limited | * 2014/10/20: Received 1kg of Field's metal and 1kg of cerrolow 136 from Lowden Limited | ||
+ | * 2014/10/02: Machining of 5 drums ready (4 of 250 mu thickness, 1 of 150 mu thickness, all without leaks) | ||
== Action items == | == Action items == | ||
* arrange a room for Willem (2014/09/18) | * arrange a room for Willem (2014/09/18) |
Revision as of 10:05, 16 November 2015
Communication
- This wiki: https://wiki.nikhef.nl/lhcb/Upgrade/RFFoil
- ELOG: https://webapps.nikhef.nl/elog/VELO_Upgrade_RFBox/
- Massi's twiki on foil thinning: https://lbtwiki.cern.ch/bin/view/VELO/FoilThinning
Planning
Link to project plan: [project plan]
Rough timeline:
- R&D/prototyping 2014-2015
- Production 2016-2017
- Installation 2018
OPP reports:
People
- Willem Kuilman
- Berend Munneke
- Johan Kos
- Martin Doets
- Rob Walet
- Tjeerd Ketel
- Wouter Hulsbergen
Drawings
The CATIA model and stp files for the RF box can be found on Martin's webpage:
http://www.nikhef.nl/~martind/Velo%20boxes/
Requirements
File:Requirements.pdf is the information given to external partners.
Information on materials
- AlMg3
- AlMg4.5
- See this link for [Wood's metal
Machining
- File:AfnameRapport DMF260-11.pdf Specification of Nikhef's DMF260-11 by the manufacturer
- File:Mul Milling vs Turning.pdf is an old presentation by Frans Mul. The interesting conclusion is that 'turning' leads to a leaking foil, while 'milling' does not.
Fixing leaks
- File:VDL Rapportage lasproeven aluminium.pdf Report by VDL (Dec 2014)
NEG coating
- File:Mul NEGcoating2005.pdf Presentation by Frans Mul on application of NEG coating at CERN
Vacuum measurements
- Dye penetrant inspection
* Information provided by Gonzalo ARNAU IZQUIERDO (materials engineer at EN/MME,CERN) * https://www.nde-ed.org/EducationResources/CommunityCollege/PenetrantTest/PTMaterials/ptmaterials.htm * http://en.wikipedia.org/wiki/Fluorescent_penetrant_inspection * Measurements were done by EN-MME Alexandre Gerardin: * https://edms.cern.ch/document/1409244/ * https://lbtwiki.cern.ch/pub/VELO/FoilThinning/Metallurgy_report_1409244.pdf * CERN can do this for the 1m long box
Presentations
This is a very small subset!
- 2015/02/05: [[1] W. Hulsbergen, CERN RF box workshop]
- 2012/03/08: File:PhotosLeakMilledFoil TjeerdKetel 20120308.pdf T. Ketel, SEM-EDS analysis of leak in VU-MC Box 1
Activities/milestones reached
- 2015/10/29: Vacuum tests show the box is vacuum tight:
- 2015/10/01: Milling now completely finished!
- 2015/09/17: Milling of outside is finished, apart from side that has wakefield connectors
* photos taken by Tjeerd: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/2015/documents/photohb2.pdf
- 2015/09/03: Mold positioned inside box and space filled with wax
- 2015/08/20: Inside milling finished
* metrology report: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/2015/documents/HalfboxA.pdf * photos taken by Tjeerd: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/2015/documents/photohb.pdf
- 2015/: Outside milled to +1 cm. This is how it will stay until inside is finished
- 2015/03/19: Mold finished
- 2014/12: Started milling of the mold
- 2014/10/20: Three drums with 0.1 micron holes sent to VDL (see ELOG)
- 2014/10/20: Received 1kg of Field's metal and 1kg of cerrolow 136 from Lowden Limited
- 2014/10/02: Machining of 5 drums ready (4 of 250 mu thickness, 1 of 150 mu thickness, all without leaks)
Action items
- arrange a room for Willem (2014/09/18)