Difference between revisions of "Upgrade/RFFoil"
Jump to navigation
Jump to search
(10 intermediate revisions by the same user not shown) | |||
Line 4: | Line 4: | ||
* ELOG: https://webapps.nikhef.nl/elog/VELO_Upgrade_RFBox/ | * ELOG: https://webapps.nikhef.nl/elog/VELO_Upgrade_RFBox/ | ||
* Progress reports in MT meetings: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/ | * Progress reports in MT meetings: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/ | ||
+ | * OPP reports: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/oppreports/VeloUpgradeRFBox/ | ||
* Massi's twiki on foil thinning: https://lbtwiki.cern.ch/bin/view/VELO/FoilThinning | * Massi's twiki on foil thinning: https://lbtwiki.cern.ch/bin/view/VELO/FoilThinning | ||
* photographs: | * photographs: | ||
** http://www.nikhef.nl/pub/departments/mt/projects/lhcb-vertex/production/UpgradeRFbox/ | ** http://www.nikhef.nl/pub/departments/mt/projects/lhcb-vertex/production/UpgradeRFbox/ | ||
** http://www.nikhef.nl/pub/departments/mt/projects/lhcb-vertex/production/UpgradeRFbox/Willem | ** http://www.nikhef.nl/pub/departments/mt/projects/lhcb-vertex/production/UpgradeRFbox/Willem | ||
+ | * RadiationTestsBirmingham | ||
== Planning == | == Planning == | ||
− | Link to project | + | Link to project plans: [https://wiki.nikhef.nl/projects/pub/Main/ProjectOverview/ProjectPlan_UpgradeVeloRFFoil.pdf 2014] |
+ | [http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/projects/VeloUpgradeRFBox/LHCb_UpgradeRFBox_2016_plan.pdf 2016 summary] | ||
Rough timeline: | Rough timeline: | ||
Line 17: | Line 20: | ||
* Production 2017-2018 | * Production 2017-2018 | ||
* Installation 2019 | * Installation 2019 | ||
+ | |||
+ | See also this [http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/projects/VeloUpgradeRFBox/RFBoxTimeline20160908.pdf detailed timeline]. | ||
OPP reports: | OPP reports: | ||
Line 39: | Line 44: | ||
== 3D model, drawings == | == 3D model, drawings == | ||
− | The CATIA model and stp files for the RF box can be found on Martin's webpage: | + | The CATIA model and stp files for the RF box can be found here: |
+ | |||
+ | http://www.nikhef.nl/pub/departments/mt/projects/lhcb-vertex/upgrade/RFfoil/ | ||
+ | |||
+ | Some /older/ drawings and pictures are on Martin's webpage: | ||
http://www.nikhef.nl/~martind/Velo%20boxes/ | http://www.nikhef.nl/~martind/Velo%20boxes/ | ||
Line 61: | Line 70: | ||
* [[File:VDL_Rapportage_lasproeven_aluminium.pdf]] Report by VDL (Dec 2014) | * [[File:VDL_Rapportage_lasproeven_aluminium.pdf]] Report by VDL (Dec 2014) | ||
+ | |||
+ | == Torlon coating == | ||
+ | |||
+ | See [[https://wiki.nikhef.nl/lhcb/Upgrade/RFFoilTorlon]RFFoilTorlon] | ||
== NEG coating == | == NEG coating == | ||
Line 89: | Line 102: | ||
== Activities/milestones reached == | == Activities/milestones reached == | ||
− | * 2015/10/29: Vacuum tests show the box is vacuum tight: https://webapps.nikhef.nl/elog/VELO_Upgrade_RFBox/8 | + | * 2016/11/22: Filling box 3 with wax |
+ | * 2016/10/01: Inside of box 3 (500 micron, full size) is finished | ||
+ | * 2016/03/31: Box 2 milling is finished | ||
+ | * 2015/10/29: Vacuum tests show the box is not vacuum tight: https://webapps.nikhef.nl/elog/VELO_Upgrade_RFBox/8 | ||
* 2015/10/01: Milling now completely finished! | * 2015/10/01: Milling now completely finished! | ||
* 2015/09/17: Milling of outside is finished, apart from side that has wakefield connectors | * 2015/09/17: Milling of outside is finished, apart from side that has wakefield connectors |
Latest revision as of 07:20, 7 June 2017
Communication
- This wiki: https://wiki.nikhef.nl/lhcb/Upgrade/RFFoil
- ELOG: https://webapps.nikhef.nl/elog/VELO_Upgrade_RFBox/
- Progress reports in MT meetings: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/
- OPP reports: http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/oppreports/VeloUpgradeRFBox/
- Massi's twiki on foil thinning: https://lbtwiki.cern.ch/bin/view/VELO/FoilThinning
- photographs:
- RadiationTestsBirmingham
Planning
Link to project plans: 2014 2016 summary
Rough timeline:
- R&D/prototyping 2014-2016
- Production 2017-2018
- Installation 2019
See also this detailed timeline.
OPP reports: [2014/02/04], [2014/04/15], [2014/07/04], [2014/09/16], [2014/10/21], [2014/12/02]
People
- Willem Kuilman
- Johan Kos
- Berend Munneke
- Krista de Roo
- Erno Roeland
- Martin Doets
- Rob Walet
- Tjeerd Ketel
- Wouter Hulsbergen
3D model, drawings
The CATIA model and stp files for the RF box can be found here:
http://www.nikhef.nl/pub/departments/mt/projects/lhcb-vertex/upgrade/RFfoil/
Some /older/ drawings and pictures are on Martin's webpage:
http://www.nikhef.nl/~martind/Velo%20boxes/
Requirements
File:Requirements.pdf is the information given to external partners.
Information on materials
- AlMg3
- AlMg4.5
- See this link for [Wood's metal
Machining
- File:AfnameRapport DMF260-11.pdf Specification of Nikhef's DMF260-11 by the manufacturer
- File:Mul Milling vs Turning.pdf is an old presentation by Frans Mul. The interesting conclusion is that 'turning' leads to a leaking foil, while 'milling' does not.
Fixing leaks
- File:VDL Rapportage lasproeven aluminium.pdf Report by VDL (Dec 2014)
Torlon coating
See [[1]RFFoilTorlon]
NEG coating
- File:Mul NEGcoating2005.pdf Presentation by Frans Mul on application of NEG coating at CERN
Vacuum measurements
- integral tests at nikhef:
- Dye penetrant inspection
- Information provided by Gonzalo ARNAU IZQUIERDO (materials engineer at EN/MME,CERN)
- Measurements were done by EN-MME Alexandre Gerardin:
Presentations
This is a very small subset!
- 2015/02/05: [[2] W. Hulsbergen, CERN RF box workshop]
- 2012/03/08: File:PhotosLeakMilledFoil TjeerdKetel 20120308.pdf T. Ketel, SEM-EDS analysis of leak in VU-MC Box 1
Activities/milestones reached
- 2016/11/22: Filling box 3 with wax
- 2016/10/01: Inside of box 3 (500 micron, full size) is finished
- 2016/03/31: Box 2 milling is finished
- 2015/10/29: Vacuum tests show the box is not vacuum tight: https://webapps.nikhef.nl/elog/VELO_Upgrade_RFBox/8
- 2015/10/01: Milling now completely finished!
- 2015/09/17: Milling of outside is finished, apart from side that has wakefield connectors
- 2015/09/03: Mold positioned inside box and space filled with wax
- 2015/08/20: Inside milling finished
- 2015/07/04: Pressure cycling tests of edged foil, see http://www.nikhef.nl/pub/experiments/bfys/lhcb/vertex/documents/minutes/2015/documents/cycletest4.pdf
- 2015/06/11: Heating box (for heating foil/mold when filling with wax) finished and tested
- 2015/04/16: Outside milled to +1 cm. This is how it will stay until inside is finished
- 2015/03/19: Mold finished
- 2014/12: Started milling of the mold
- 2014/10/20: Three drums with 0.1 micron holes sent to VDL (see ELOG)
- 2014/10/20: Received 1kg of Field's metal and 1kg of cerrolow 136 from Lowden Limited
- 2014/10/02: Machining of 5 drums ready (4 of 250 mu thickness, 1 of 150 mu thickness, all without leaks)